Designs Wayzata Boulevard road improvements

Hennepin County file 26-0229, before the Hennepin County Board. Passed as of 2026-07-14.

Latest action: Approved

What it does

Planning work starts for Wayzata Boulevard fixes Bolton & Menk Inc. will spend up to $1.4 million studying and designing changes to Wayzata Boulevard and Central Avenue to prepare for construction.

The bigger picture

Road work may take months before actual construction This preliminary design work can take 12-18 months; actual road repairs won't start until after the plans are done and approved.

What to watch

Funding covers only planning, not the actual work This $1.4 million pays for design only; the county will need separate funding later to actually build or fix the road.

Read the official record for 26-0229

Weigh in on this matter · This week in Hennepin County · See what we have filed with the clerk