Fire Station 4 renovation costs increase $120K

File 26-1237 ("Fire Station 4 renovation costs increase $120K") is before Naperville and has not been decided. Latest step (November 4, 2026): Agenda Ready.

Naperville file 26-1237, before Naperville. Still to be decided as of 2026-11-04.

What it does

Fire Station 4 work extended by two months The renovation project will take an additional 61 days to complete, pushing the finish date further out and keeping the station partially disrupted during construction.

The bigger picture

Overall project cost rises to just over $3 million The change order adds $120,145 to the contract, raising total spending to $3,018,145 for the Fire Station 4 improvements.

What to watch

Extended timeline may delay return to full station capacity The additional 61 days means Fire Station 4 will remain in a reduced state longer, which could affect emergency response readiness in that area while renovation work continues.