Naperville approved file 26-1011 ("Underground electrical work contract renewal"), by a recorded vote of 9 to 0. Last action: October 20, 2026.
Naperville file 26-1011, before Naperville. Passed as of 2026-10-20.
Nearly $20 million for underground electrical work Naperville will spend up to $19.9 million on burying electrical lines, boring under streets, and related services through two companies.
Ongoing grid upgrades reduce power outages from storms Underground lines are less likely to fail during bad weather, so your neighborhood should see fewer blackouts as this multi-year work continues.
Street disruptions likely during boring and installation work Directional boring and line installation will mean temporary road closures, noise, and traffic delays in neighborhoods where crews are working.
Read the official record for 26-1011
See everything up for a vote · This week in Naperville · See what we have filed with the clerk