Naperville approved file 26-0881 ("Ogden and Washington water main work extended"). Last action: August 18, 2026.
Naperville file 26-0881, before Naperville. Passed as of 2026-08-18.
Work on your street will take 238 more days Ogden Avenue and Washington Street water main work will run an extra 8 months past the original deadline, adding about $343,000 to the final cost.
Water system upgrades continue despite delays The city is still improving aging water lines in this area, which helps prevent breaks and keeps service reliable for you and your neighbors.
Project costs rose by 7 percent more than planned The extra work and time cost about $343,000 more than the original deal, which may affect other city projects or require additional funding.