Naperville file 26-0558, before Naperville. Still to be decided as of 2026-11-17.
Latest action: Agenda Ready
Power equipment repairs continue without service interruption The extra funding ensures the substation transformer work finishes on schedule, maintaining reliable power delivery to the tollway and surrounding areas.
Keeps tollway operations stable during maintenance work Completing transformer upgrades on time reduces risk of unexpected power outages that could disrupt tollway traffic or delay future infrastructure projects.
Change order signals original bid underestimated actual scope The $36,500 increase suggests the initial $297,763 contract price did not fully account for the work required, raising questions about how closely city staff reviewed the scope before awarding the original contract.
Read the official record for 26-0558