Minneapolis file 2026-01118, before the Minneapolis City Council. Still to be decided as of 2026-10-08.
Latest action: Approved by Climate & Infrastructure Committee
Construction work continues on busy intersection Thomas & Sons Construction gets an extra $100,000 to complete safety upgrades at 26th Street East and Hiawatha Avenue.
Delays and traffic disruptions likely continue longer Additional construction work means the safety project will take more time, keeping traffic impacts and street closures in effect in that area.
Authorizing an increase to contract COM0011383withThomas & Sons Construction Inc.in theamount of $100,000for a total amount not to exceed $3,024,275,foradditional work to complete the 26th Street East and Hiawatha Avenue Safety Improvement Project, all in accordance with City specifications.