The Minneapolis City Council approved file 2026-00850 ("Columbia Heights water plant roof replacement"), by a recorded vote of 12 to 0. Last action: August 8, 2026.
Minneapolis file 2026-00850, before the Minneapolis City Council. Passed as of 2026-08-08.
Water plant gets new roof this year The city spends $2.2 million to replace the aging roof at Columbia Heights Membrane Plant, protecting the facility that treats Minneapolis water.
Prevents future water system disruptions and costly emergencies A new roof keeps the plant running reliably without leaks or damage that could interrupt water treatment or force emergency repairs.
Project costs add to city budget and water bills The $2.2 million contract comes from the city budget; residents may see this reflected in water rate discussions or capital spending priorities.
Accepting the low bid of Dura-Roof, LLC., submitted on Event 3975, in the amount of $2,200,000, to provide all materials, labor, equipment, and incidentals necessary for the Columbia Heights Membrane Plant Roof Replacement, and authorizing a contract for the project, all in accordance with City specifications.
Read the official record for 2026-00850
See everything up for a vote · This week in Minneapolis · See what we have filed with the clerk