22nd Ave sewer design

The Minneapolis City Council approved file 2026-00702 ("22nd Ave sewer design"), by a recorded vote of 12 to 0. Last action: July 7, 2026.

Minneapolis file 2026-00702, before the Minneapolis City Council. Passed as of 2026-07-07.

What it does

Design work begins for your neighborhood's aging pipes The city is paying $4.4 million to plan how to replace old storm and sewer lines under 22nd Ave NE, which will determine when construction starts and how long it takes.

The bigger picture

Fixes wet basement and street flooding problems Better storm and sewer pipes reduce basement backups and street flooding during heavy rain, which affects the whole Northeast Minneapolis neighborhood.

What to watch

Construction delays and costs may exceed current plans This contract only covers planning and design—the actual rebuild will cost more and take years, during which 22nd Ave will likely see lane closures and traffic disruptions.

Official summary

Authorizing a contract with Foth Infrastructure & Environment, LLC, in the amount of $4,443,429, for engineering and design services of 22nd Ave NE Storm and Sanitary Sewer Reconstruction project.

How they voted

Yes (12)

Did not vote / other (1)

Read the official record for 2026-00702

See everything up for a vote · This week in Minneapolis · See what we have filed with the clerk