The Minneapolis City Council approved file 2026-00612 ("Bossen Terrace sewer project cost increase"), by a recorded vote of 13 to 0. Last action: June 23, 2026.
Minneapolis file 2026-00612, before the Minneapolis City Council. Passed as of 2026-06-23.
Sewer work near Bossen Terrace runs longer Construction continues through July 2027 instead of ending sooner, meaning ongoing traffic detours and noise in the area.
Better drainage and sewage handling for residents The extra funding and time allow workers to improve storm and sanitary sewer lines, reducing flooding and overflow risks in Bossen Terrace.
Higher costs passed to taxpayers eventually The $390,000 increase comes from public funds; residents may see this reflected in future water bills or property taxes.
Authorizing an increase to contract COM0008704 with Minger Construction Companies, Inc., in the amount of $390,075.08 for a total amount not to exceed $6,866,747.12, and an extension through July 31, 2027, for construction work on the Bossen Terrace Sanitary & Storm Sewer Improvements project.