Fridley water plant repair funding approved

The Minneapolis City Council approved file 2026-00050 ("Fridley water plant repair funding approved"), by a recorded vote of 13 to 0. Last action: February 14, 2026.

Minneapolis file 2026-00050, before the Minneapolis City Council. Passed as of 2026-02-14.

What it does

Water plant repairs continue on schedule The city is spending an extra $214,744 to fix the Fridley Softening Plant building, keeping water treatment on track through April 2026.

The bigger picture

Keeps water quality and system reliability steady Repairing the plant's structural damage prevents service interruptions and protects the water system that serves Minneapolis residents.

What to watch

Project costs growing beyond original contract The total contract has grown from an initial amount to $2.05 million; if repairs take longer than April 2026, another budget increase may be needed.

Official summary

Authorizing an increase to contract COM0007389 with PCI Roads, LLC, in the amount of $214,744.73 for a total amount not to exceed $2,052,786.69, and a contract extension through April 30, 2026,for construction of structural repairs for the Division of Water Treatment & Distribution Services' Fridley Softening Plant building.