South Minneapolis safety center design cost increase

The Minneapolis City Council approved file 2026-00049 ("South Minneapolis safety center design cost increase"), by a recorded vote of 13 to 0. Last action: February 14, 2026.

Minneapolis file 2026-00049, before the Minneapolis City Council. Passed as of 2026-02-14.

What it does

Design delays add $78,000 to project cost The city is spending an extra $78,000 on architectural and engineering work for the South Minneapolis Community Safety Center, bringing the total design contract to $1.076 million.

The bigger picture

Overall project timeline and final budget still under development Additional design services typically signal scope changes or complexity that may affect the full project cost and when the center opens to serve the neighborhood.

Official summary

Authorizing an increase to Contract No. COM0008644 with Wold Architects & Engineers, in an amount of $78,000for a total amount not-to-exceed $1,076,000, for additional architectural and engineering design services for the South Minneapolis Community Safety Center.

How they voted

Yes (13)

Read the official record for 2026-00049

See everything up for a vote · This week in Minneapolis · See what we have filed with the clerk