The Minneapolis City Council approved file 2026-00028 ("Convention center meeting room remodel cost increase"), by a recorded vote of 13 to 0. Last action: February 14, 2026.
Minneapolis file 2026-00028, before the Minneapolis City Council. Passed as of 2026-02-14.
Convention center remodel costs $489K more than planned The city is spending an additional $488,803 to finish Phase 3 of the meeting room renovation, raising the total contract price to $10.4 million.
Updated meeting spaces may attract more conferences and events Better meeting rooms could help Minneapolis draw bigger conventions and business events, boosting hotel bookings and restaurant traffic downtown.
Project costs have grown beyond original budget estimate Change orders suggest renovation work cost more than expected, and this pattern may continue if unforeseen issues arise during remaining construction phases.
Authorizing an increase to Contract No. COM0009562with Sheehy Construction Company, in the amount of $488,803.21, for a total amount not to exceed $10,375,824.21, for change ordersneeded to complete the Minneapolis Convention Center Meeting Rooms Remodel - Phase 3Project.