The Minneapolis City Council approved file 2025-01347 ("Lead pipe replacement work continues through 2025"), by a recorded vote of 9 to 0. Last action: December 20, 2025.
Minneapolis file 2025-01347, before the Minneapolis City Council. Passed as of 2025-12-20.
Your lead pipes get replaced faster with extra funding The city is spending an extra $671,576 to speed up lead service line removals and finish winterization work by the end of 2025.
More homes avoid long-term health risks from lead water Completing lead pipe replacements sooner means more Minneapolis families drink safe water now instead of facing years of delayed work.
Work timeline depends on weather and contractor capacity Winter conditions can slow outdoor pipe work, and project completion relies on Q3 Contracting finishing all jobs by December 2025.
Authorizing an increase to contract COM0009949 with Q3 Contracting, Inc., in the amount of $671,576for a total amount not to exceed $1,029,415.82, for additional workneeded to winterizeand completethe restoration work for the Lead Service Line Replacements performed through December 2025.
Read the official record for 2025-01347
See everything up for a vote · This week in Minneapolis · See what we have filed with the clerk