Adds $346K to Logan Park engineering contract

The Minneapolis City Council approved file 2025-01271 ("Adds $346K to Logan Park engineering contract"), by a recorded vote of 9 to 0. Last action: December 20, 2025.

Minneapolis file 2025-01271, before the Minneapolis City Council. Passed as of 2025-12-20.

What it does

Design work takes longer; project timeline may shift The city is paying $345,906 more to the engineering firm for additional work on the Logan Park rebuild project, which may delay when construction can start.

The bigger picture

Industrial site improvements move forward despite higher costs The Logan Park Industrial Reconstruction project continues; the extra spending suggests more design complexity than first expected, but the city is committing to finish the planning phase.

What to watch

Total project cost now approaches $1.9 million for design alone The full contract with the engineering firm now reaches $1.91 million; residents should expect updates on final construction costs and overall project timeline.

Official summary

Authorizing an increase to contract COM008238 with Short Elliot Hendrickson, Inc., in the amount of $345,906.71 for a total amount not to exceed $1,911,110.71, for additional engineering and design services for Logan Park Industrial Reconstruction project, all in accordance with City specifications.

How they voted

Yes (9)

Read the official record for 2025-01271