Milwaukee approved file 260314 ("West National Avenue redesign cost shift"), by a recorded vote of 15 to 0. Last action: June 23, 2026.
Milwaukee file 260314, before Milwaukee. Passed as of 2026-06-23.
Your street project costs the city more money Milwaukee will pay an extra $2.5 million toward redesigning West National Avenue from 39th to 1st Street, while the state contributes $2.7 million less than originally planned.
Less state funding means more pressure on city budget This deal shifts a larger share of highway project costs to Milwaukee, reducing what the state covers and potentially limiting money available for other city projects.
City takes on bigger cost while total project savings unclear Although the overall project cost drops by $203,700, Milwaukee residents bear most of that burden through higher city spending, while the state's contribution shrinks significantly.
See everything up for a vote · This week in Milwaukee · See what we have filed with the clerk