The Illinois Legislature approved file SB3273 ("Speeds up renewable energy credits for schools"), by a recorded vote of 165 to 0. Last action: July 10, 2026.

Illinois file SB3273, before the Illinois Legislature. Passed as of 2026-07-10.

What it does

Schools receive solar credits within 90 days guaranteed Public schools installing distributed renewable generation now receive net metering credits or other utility credits within 90 days of approval, rather than indefinite delays.

The bigger picture

Level playing field for solar interconnection across utility types Electric cooperatives and municipal utility systems must now charge interconnection fees at or below 150% of what major utilities charge, removing barriers that previously made solar projects more expensive for schools served by smaller utilities.

What to watch

Rules apply only to public school renewable projects Private schools, nonprofits, municipal buildings, and other entities installing distributed solar on their own land are not covered by the faster credit timeline or fee standardization requirements.

Official summary

Amends the Public Utilities Act. Sets forth procedures for the processing of interconnection requests from applicants for distributed renewable generation projects on public school land. Provides that, for all net metering credits or other credits owed to a customer who has elected to install a distributed renewable generation project on public school land, all credits intended for the benefit of the consumer must be credited by the public utility or retail energy supplier within 90 days after the public utility or retail energy supplier determines that the criteria for the credit have been met. Provides that the Illinois Commerce Commission shall adopt revisions to its standards for the interconnection of eligible renewable generating equipment and net metering credit rules to conform with the requirements of the provisions of the amendatory Act. In provisions concerning customer self-generation of electricity, provides that, for distributed renewable generation projects on public school land, any fees for interconnection applications charged by the electric cooperative or municipal system must be substantially similar to the fees charged by public utilities for the interconnectio

How they voted

Yes (165)

Did not vote / other (10)