Fresno approved file ID 26-1394 ("Approve Contract Change Order No. 3 in the amount of $2,804.25 with forty-four (44) additional working days for the installation of one (1) solar power irrigation controller, cost credit for omitting the removal of pole bases and the installation of a power feed for the existing streetlights, bringing the new Construction Contract total to $7,037,639.37 with $509,224.26 remaining in contingency, with Yarbs Grading and Paving, Inc. of Fowler CA for the MLK Center Active Transportation Infrastructure project located on Martin Luther King Jr. Boulevard between Church Avenue and Jensen Avenue - Project ID PW00842 (Council District 3)"), by a recorded vote of 6 to 0. Last action: November 5, 2026.
Fresno file ID 26-1394, before Fresno. Passed as of 2026-11-05.
Read the official record for ID 26-1394
See everything up for a vote · This week in Fresno · See what we have filed with the clerk