Duluth approved file 26-0808R ("Upper Lakeside water line upgrade"). Last action: September 14, 2026.
Duluth file 26-0808R, before Duluth. Passed as of 2026-09-14.
Water service improvements for north Duluth residents The city would spend $268,625 to connect the Upper Lakeside water zone to improve service reliability and water flow in that area.
Part of larger water system upgrade plan This Phase 2 project is part of a multi-year effort to make the city's water network more flexible and better able to handle demand across different zones.
Only addresses one zone; other areas may wait The project focuses on Upper Lakeside only, so residents in other parts of the city waiting for similar water system work may face longer delays.