Denver approved file 26-1506 ("A resolution approving a proposed Contract between the City and County of Denver and Inliner Solutions, LLC for the 2026 WMD Pipe and Manhole Rehabilitation, Phase 2 project which will rehabilitate deteriorating sanitary pipes and manholes using trenchless methods, citywide. Approves a contract with Inliner Solutions, LLC for $4,104,481.00 with an term of NTP + 365 Days for the 2026 WMD Pipe and Manhole Rehabilitation, Phase 2 project which will rehabilitate deteriorating sanitary pipes and manholes using trenchless methods, citywide (DOTI-202684947). The last regularly scheduled Council meeting within the 30-day review period is on 11-16-2026. The Committee approved filing this item at its meeting on 10-21-2026."), by a recorded vote of 11 to 0. Last action: October 26, 2026.
Denver file 26-1506, before Denver. Passed as of 2026-10-26.
Read the official record for 26-1506