Chicago file O2026-0028838, before Chicago. Still to be decided as of 2026-09-23.
Latest action: Two committees having been called, the Committee on Zoning, Landmarks and Building Standards and the Committee on Finance, the matter was referred to the Committee on Committees and Rules (Pursuant to Council Rule 42)
Companies cannot apply for new data centers If passed, any company wanting to build or expand a data storage facility in Chicago would have to wait until the city lifts the freeze.
Energy use and grid strain concerns get time The pause lets the city study how data centers affect power demand and local utilities before approving more facilities.
Delay may push projects to neighboring cities Companies seeking to expand may choose to build in suburbs instead, meaning Chicago could lose the tax money and jobs those centers would bring.
See everything up for a vote · This week in Chicago · See what we have filed with the clerk