Charlestonsc approved file CHS-20260922-L1-2 ("Approval of Lowline Revised Early Site Package Scope of Work Change Order #5 to facilitate a remobilization date of 10/19/26. The Change Order amount is $2,006,204.00. This Change Order must be approved by COB September 22, 2026 to maintain revised Early Site Package construction package. This will..."). Last action: September 22, 2026.
Charlestonsc file CHS-20260922-L1-2, before Charlestonsc. Passed as of 2026-09-22.
Approval of Lowline Revised Early Site Package Scope of Work Change Order #5 to facilitate a remobilization date of 10/19/26. The Change Order amount is $2,006,204.00. This Change Order must be approved by COB September 22, 2026 to maintain revised Early Site Package construction package. This will be funded by the Cooper River Bridge TIF.
Read the official record for CHS-20260922-L1-2